[PROJECT 06 · Finland]

RECION OY — Carbon Steel Pipe Prefabrication

Prefabrication of black steel piping systems of various diameters. Fabrication of pipe spools and welded assemblies for industrial installation.

[CLIENT]
RECION OY
[COUNTRY]
Finland
[INDUSTRY]
POWER-ENERGY
[PERIOD]
Jun 2024 — Jul 2024

[FULL SPECIFICATION]

[CLIENT]
RECION OY
[COUNTRY]
Finland
[INDUSTRY]
POWER-ENERGY
[PERIOD]
Jun 2024 — Jul 2024
[DURATION]
2 months
[DELIVERED VIA]
Cj Consulting AB
[SERVICES]
pipe prefabricationindustrial welding

RECION OY — Carbon Steel Pipe Prefabrication

Client: Cj Consulting AB (main contractor) Site: RECION OY facility, Finland Industry: Power & Energy / Industrial Period: June – July 2024 Services: Pipe Prefabrication · Industrial Welding


Context

RECION OY is a Finnish industrial firm active in piping and heavy mechanical work. The June-July 2024 engagement was MIDAS’s first Nordic campaign delivered under a main-contractor model and a key early project in establishing our Finnish market presence.

Prefabrication for an industrial client requires tight tolerances, traceability, and predictable output. Unlike turnaround work, where the pressure is the outage window, prefab pressure is cumulative — so many spools due per week to feed a downstream installation programme, with any delay rippling forward into site delivery dates.

Scope

Two months of prefabrication delivery, June-July 2024:

  • Prefabrication of black steel (carbon steel) piping systems
  • Cutting, bevelling, fit-up and welding across various pipe diameters
  • Fabrication of pipe spools and welded assemblies for subsequent industrial installation
  • Documentation and handover per spool

The pipe diameters varied across the scope — standard industrial process piping diameters in carbon steel, typical of a process industry or power facility application.

Approach

Prefab campaigns benefit from process discipline above all else:

  • Material staged by spool ID on receipt
  • Welder allocation matched to spool class (small-bore TIG specialists vs. larger MAG/SMAW welders)
  • Daily output tracking against the delivery schedule
  • Documentation generated in parallel with production — test pack filled in as welds are produced, not after the fact

The RECION OY campaign ran cleanly through the two-month window. It also served as the template for how we’d later approach the larger Stegra prefabrication campaign — same disciplines, scaled up.

Outcome

Completed spool production delivered to RECION OY on schedule, with full traceability documentation per spool. The project is the basis of our Finnish track record claim and demonstrated MIDAS’s ability to work through Nordic main contractor structures outside Sweden.

Technical summary

ScopeCarbon steel pipe spool prefabrication
StandardsISO 3834-2, EN 13480-4
Welding processes141 TIG, 135 MAG, 111 SMAW
MaterialCarbon steel, ISO/TR 15608 group 1.1
DurationJune – July 2024
Delivered viaCj Consulting AB

Request a quote for a similar project

If you have a carbon-steel pipe prefabrication programme and need a proven Nordic-market subcontractor, send us the scope and schedule.

CTA: Request a Quote Secondary: View all projects

RECION OY Cj Consulting AB Finland 2 months RECION OY Cj Consulting AB Finland 2 months

[REQUEST]

Have a similar project?

[REQUEST A QUOTE] →