[PROJECT 01 · Sweden]

St1 Refinery — Three-Phase Turnaround Campaign

Three consecutive turnaround campaigns across refinery shutdown windows — furnace repair, welding, piping installation, and new process equipment installation.

[CLIENT]
St1 Refinery
[END OPERATOR]
St1 Nordic Oy
[COUNTRY]
Sweden
[INDUSTRY]
OIL-REFINERIES

[FULL SPECIFICATION]

[CLIENT]
St1 Refinery
[END OPERATOR]
St1 Nordic Oy
[COUNTRY]
Sweden
[INDUSTRY]
OIL-REFINERIES
[PERIOD]
Nov 2024 — Apr 2025
[DURATION]
5 months (3 campaigns)
[DELIVERED VIA]
WP Welding AB
[SERVICES]
industrial weldingpipeline installationmaintenance turnaroundsequipment installation

St1 Refinery — Three-Phase Turnaround Campaign

Client: WP Welding AB (main contractor) Site: St1 Refinery, Sweden Industry: Oil & Gas · Refinery Period: November 2024 – April 2025 Services: Industrial Welding · Pipeline Installation · Maintenance & Turnarounds · Equipment Installation


Context

St1 operates one of Sweden’s key refineries, supplying domestic and regional fuel markets. Like most operating refineries, it runs on a rolling turnaround programme — scheduled outage windows during which furnaces, heat exchangers, columns, and process piping are inspected, repaired, or replaced.

In late 2024, WP Welding AB — a Swedish welding main contractor — was scoped to deliver welding and mechanical works across three sequential St1 outage campaigns. The challenge wasn’t any single window. It was the cumulative reliability required across three back-to-back campaigns: the same crews, the same documentation discipline, the same safety record, delivered three times in a row with no slip between windows.

MIDAS was brought in as WP Welding AB’s welding subcontractor for all three phases.

Phase 1 — Furnace Turnaround, November–December 2024

Scope: Refinery turnaround works focused on furnace repair. Welding and installation of process piping in confined and hard-to-access areas under active PTW regime.

Furnace work is some of the hardest welding in a refinery environment. Access is tight. Preheat is typically required. The position is often overhead or 6G. And the consequence of a weld defect on a furnace tube is a forced outage extension nobody can afford.

Our crew delivered:

  • Welding of furnace-adjacent piping per client WPS
  • Repair welding of identified weld defects and corroded sections
  • Integration into daily PTW briefings and hot work permit procedures
  • Full weld documentation and traceability to welder ID

Phase 1 handed over on schedule with all welds accepted on first-pass inspection for the critical scope.

Phase 2 — Furnace Turnaround Continuation, January 2025

Scope: Repair of Furnace No. 2 during a subsequent shutdown, mid-January to end of January 2025. Welding and piping installation works.

Phase 2 came two weeks after Phase 1 handover. For MIDAS, this meant demobilizing and re-mobilizing the same crew back to the same site within a window too short for any new welder qualification testing. Our welding coordination had the qualification matrix ready, the scope was pre-briefed, and the crew walked back onto site pre-inducted.

Delivered:

  • Furnace tube and header welding
  • Process piping installation and tie-ins
  • Continued integration into main contractor’s QA/QC documentation stream

The back-to-back nature of Phase 1 → Phase 2 is what the St1 case study demonstrates more than any individual scope element: our crews can be re-deployed on consecutive windows without ramp-up time loss.

Phase 3 — Equipment Installation, March–April 2025

Scope: Turnaround works at the refinery focused on equipment installation. Installation of new process equipment and associated piping systems.

Phase 3 shifted focus from repair to new-build-in-place. Process equipment — new units installed on existing foundations, tied in to existing process piping — requires both mechanical installation discipline and welded tie-in integrity.

Delivered:

  • New equipment placement coordination
  • Tie-in welding to existing process piping
  • New piping fabrication for tie-in spools
  • Pressure testing and handover to commissioning

Outcome

Across the three-phase campaign, MIDAS delivered:

  • Welding and piping scope across five months of intermittent outage windows
  • Back-to-back crew deployment across all three campaigns
  • Full documentation handover per phase
  • Integration with WP Welding AB’s main contractor QA/QC and HSE systems

The reliability of delivering three consecutive St1 outage windows has made the St1 campaign MIDAS’s most-referenced project to date — and the proof point behind our “mobilization speed” claim.

Technical summary

ScopeFurnace repair, process piping, equipment installation
StandardsISO 3834-2, EN 13480, client plant-specific specs
Welding processes141 TIG, 135/136 MAG, 111 SMAW
MaterialsCarbon steel pressure grades
Access conditionsConfined, overhead, positional, hot work PTW
Duration3 campaigns, November 2024 – April 2025
Delivered viaWP Welding AB

Request a quote for a similar project

If you’re planning a refinery turnaround or back-to-back outage campaigns, we’d like to hear the scope. Send us your window dates, scope, and standards. We’ll respond within one business day.

CTA: Request a Quote Secondary: View all projects

St1 Refinery WP Welding AB Sweden 5 months (3 campaigns) St1 Refinery WP Welding AB Sweden 5 months (3 campaigns)

[REQUEST]

Have a similar project?

[REQUEST A QUOTE] →